# SecureCam ideal project Gantt chart ```mermaid gantt title SecureCam Project Timeline dateFormat YYYY-MM-DD axisFormat %b excludes weekends section Initiation and Planning Project scoping and proposal :done, a1, 2025-10-15, 10d Requirements gathering and research :done, a2, after a1, 12d Early architecture and feasibility :done, a3, after a1, 15d section Initial Prototype Core prototype implementation :done, b1, 2025-10-28, 18d Basic camera-to-client workflow :done, b2, after b1, 10d section Scope Change and Refactor Major scope change identified :milestone, m1, 2025-11-12, 0d Requirements redefinition :crit, c1, 2025-11-13, 8d Architecture redesign :crit, c2, after c1, 10d Backend refactor and model cleanup :crit, c3, after c2, 18d Web and mobile flow realignment :crit, c4, after c2, 14d section Platform Rebuild Authentication and device model :d1, 2025-12-09, 12d Realtime communication layer :d2, after d1, 14d Stream control and recording pipeline :d3, after d2, 16d Storage integration and signed media URLs :d4, after d1, 12d Motion events and activity feed :d5, after d2, 10d section Client Applications Web app feature completion :e1, 2026-01-20, 18d Mobile app implementation :e2, 2026-01-27, 24d Push notifications and user feedback loop :e3, after d5, 12d section Quality and Evaluation Integration testing and bug fixing :f1, 2026-02-24, 18d Performance tuning and resilience review :f2, after f1, 10d Final validation and demo preparation :f3, after f2, 8d section Dissertation and Delivery Documentation and architecture diagrams :g1, 2026-03-17, 12d Report writing and iteration :g2, 2026-03-10, 26d Final edits and submission prep :g3, after g2, 8d Project complete :milestone, m2, 2026-04-17, 0d ``` ## Notes - Start date assumed: `2025-10-15` to reflect a mid-October project start. - Final deadline set to: `2026-04-17`. - The chart assumes a major scope shift in mid-November that forced the team to revisit requirements and refactor the platform. - The refactor is treated as a real disruption rather than a minor iteration, so the later phases are shown as a rebuild on firmer architecture rather than a straight continuation of the original prototype. - This is an "idealised but realistic" plan for documentation purposes, not a claim that every task happened exactly in this order.